View of the new framing for the ceiling and the now electrified can lights.
Viewed: 563 times.
|
Plumbing for the new sink on the west wall of the kitchen
Viewed: 499 times.
|
Electrical for wall outlets and dishwasher on the west wall of the kitchen.
Viewed: 549 times.
|
Wall repair work on the south wall of the kitchen
Viewed: 507 times.
|
View of the framing work that will define the wall for the refridgerator and the walk-in pantry/closet behind
Viewed: 457 times.
|
Repair work to the north wall of the kitchen where we found the remains of two walls that had been removed by the previous owner
Viewed: 456 times.
|
More repair work on the north wall of the kitchen.
Viewed: 448 times.
|
Plumbing for the water supply for the ice maker in the refridgerator.
Viewed: 461 times.
|
Framing for the door that was to be the entrance of the walk in pantry/closet. This was changed very early on in the project.
Viewed: 483 times.
|
View of the framing work where the refridgerator will go. Originally we had planned for the door to the walk-in pantry to be beside the kitchen, but we did a mid-course correction and decided to put a pantry cabinet where the door was supposed to go.
Viewed: 445 times.
|
View of the ceiling of the southeast corner of the kitchen with new framing.
Viewed: 433 times.
|
View of the northwest corner of the kitchen with the new subflooring
Viewed: 511 times.
|